| Direct
              changeover
                 
             | 
            The old system is stopped and the following day the
              new system is used.
               This could be disastrous if there are errors in the new
              system! 
             | 
          
          
            | Parallel
              running
                 
             | 
            The old system and the new system are run  together
              for a period of time. The old system is stopped only when it is
              certain that the new system is running correctly.
               Advantage : no
              disasters if there are errors in the new system 
              Disadvantage : a
              lot of duplication of work. 
             | 
          
          
            | Piloting
                 
             | 
            The new system could be tried by part of the
              company - eg one branch.
               If all goes well, then the rest of the company can change to
              the new system 
             | 
          
          
            | Phased
              change | 
            Part of the new system is used, and when all
              problems have been solved and it works then another part is
              implemented and so on... 
             |